A project manager is assigned to lead an enterprise transformation to address change and value delivery at the organizational level. The project manager is working with the team to deliver incremental changes.
What should the project manager do to ensure the success of this endeavor at both the team and organizational levels?
Having managed a similar project while working with previous stakeholders, a project team decided to use the same report format they used in the earlier project. However, stakeholders new to the project are not fully comprehending the status of the project based on the reports that are being circulated.
How should the project manager address this concern moving forward?
A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project.
What should the project manager do to alleviate the stakeholders' concerns?
A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?
A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time.
What should the project manager do next?
In an ongoing project, the customer, who has been the main contact for the project, informs the project manager that they will be introducing a new contact person due to their busy schedule.
Moving forward, the new contact will also be making key decisions.
What should the project manager do next?
Most of the work packages for a project are subcontracted. In the middle of execution, the project manager is informed that a new contract manager will take the position in one-week.
What should the project manager do next?
During the early phases of a project, mitigation actions were not executed in a timely manner; therefore, the project schedule was impacted. Several project stakeholders are now frustrated with the delays.
What should the project manager have done to manage the issue?
A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project.
How should the project manager report this cost?
Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration. The product owner seems much more interested in the cost rather than the product itself.
What should the project manager have done earlier to change the product owner's behavior?