PMI PMP Practice Test - Questions Answers, Page 91
List of questions
Related questions
A project manager writes to the receiving organization to inform them that all acceptance activities are completed with success and it's time to initiate handover. The receiving manager replies that the team will not be ready for the handover procedure for another two weeks.
What should the project manager do?
A project manager is working on a hybrid project that has been in progress for the last nine months. Some project stakeholders are becoming frustrated because they do not see the value added by the project.
What should the project manager do to demonstrate the project value?
A project sponsor receives project information and updates in a timely manner, but the sponsor is concerned because key information is missing in the reports. What should the project manager do?
A project manager is assigned to a parachute development project. Two of the key project resources have a disagreement regarding a requirement.
What should the project manager do?
During the execution phase, the project manager discovered that the deliverables are not meeting the quality specifications requested by the main stakeholder. This has caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost performance index (CPI) from 1.5 to 1.1.
What action should the project manager take to mitigate the issue of the deliverables being rejected during the next iteration?
A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts. However, a few stakeholders are reporting that they are unable to find the latest project schedule.
What should the project manager do?
A project's planning phase has just been completed and was defined by team members in remote sessions. The day after the kick-off meeting, which was held at the client facilities, team member A asked the project manager to be moved to another project because they were uncomfortable around team member B.
What should the project manager do to deal with this situation? (Choose two.)
A project team member identified a defect in the initial solution design for a project. The stakeholders are not sure whether to deploy the system or not.
What should the project manager do?
A project manager has experience working with a specific provider that has been requested for an upcoming project. This provider often fails to meet deliverable dates; however it is the only company with the specific experience required for the project.
What should the project manager do during the planning phase?
In a standup meeting, a team member has been providing the same update for five consecutive days. The task, which is on the critical path, is now at risk for delaying the schedule.
What should the project manager do?
Question