ExamGecko
Home / PMI / PMP / List of questions
Ask Question

PMI PMP Practice Test - Questions Answers, Page 100

Add to Whishlist

List of questions

Question 991

Report Export Collapse

For the second time in a week, one of the team members failed to deliver their assigned work. As a result, it is impossible for the team to achieve their agreed-upon target.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 992

Report Export Collapse

After releasing the first deliverable of the project, one of the impacted departments refused to use the system because they believe that it adds more work. What could the project manager have done to prevent this?

Become a Premium Member for full access
  Unlock Premium Member

Question 993

Report Export Collapse

In the execution phase of a large construction project, the contracted logistic company decided to increase their price as a result of unavailability of shipping containers. What should project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 994

Report Export Collapse

A new project needs to be kicked off in an organization that has regulatory requirements defined in their organizational governance process. How should the project manager define the project governance?

Become a Premium Member for full access
  Unlock Premium Member

Question 995

Report Export Collapse

A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 996

Report Export Collapse

Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.

Which three actions should the project manager do? (Choose three.)

Become a Premium Member for full access
  Unlock Premium Member

Question 997

Report Export Collapse

A project team is finishing a sprint to deliver a key deliverable. The project team tells the project manager that the deliverable does not meet the agreed project standards set out by the customer and insists on reworking the deliverable to meet the standards. This will delay the project by two weeks.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 998

Report Export Collapse

A project manager noticed that a talented team member remains passive and quiet during project meetings with the larger project team and other stakeholders. The team member interacts with the project manager quite well during one-on-one interactions.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 999

Report Export Collapse

A customer approaches the product owner with a new requirement and asks for a rough estimation to implement it. The outline of the task would be similar to a prior deliverable.

What should the product owner do to properly inform the customer?

Become a Premium Member for full access
  Unlock Premium Member

Question 1000

Report Export Collapse

An internal process was recently introduced by the management team. The new process, however, has not added much value and is impacting the project's deliverables.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member
Total 1.477 questions
Go to page: of 148
Search

Related questions