PMI PMP Practice Test - Questions Answers, Page 101
List of questions
Related questions
During a project gate review meeting, it is identified that one of the project deliverables will require corrective actions to meet the project quality requirements. What should the project manager do first?
A project team has identified a risk and wants to accept it as an opportunity to finish a project earlier than planned. The project manager realizes that the sponsor may not accept the risk since the sponsor is risk averse.
What should the project manager do?
One of the team members is always late to the daily standup meeting. What should the project manager do?
A project team is facing challenges understanding how to deliver a project's scope. A senior subject matter expert (SME) from the organization's global office is in town for 1 week.
What should the project manager do to benefit from the SME's presence?
A client has requested that a product be implemented in 4 months and is ready to increase their budget to do this quickly. The project manager cannot comply with the request with the current resources or even additional resources. The project manager estimates that 8 to 12 months are needed for the product to go live.
What should the project manager do to address this situation?
A project manager has recently been asked to take over an existing project. The project manager would like to determine how the project has been progressing by tracking features that are in progress. completed. or scheduled to be worked on.
Which of the following can help the project manager assess the state of the project?
An information technology (TT) team is responsible for the validation and release of a product developed by the agile development team. Due to other priorities for the IT learn, the releases are delayed.
What action should the project manager take?
A project team is executing a project to replace an existing system with a new one. A new project manager has been hired and observes that the team consist of professionals who have worked with the older system, and others who have little previous experience.
What should the project manager do to ensure project success?
During project execution, a client asks to add one more features to the product. After performing a change request analysis, the project manager realizes the necessary equipment will not be available in time to support this new feature, resulting in the project team being idle.
What should the project manager do next?
A project for developing software for a retail company's procurement system is in the initiation phase. The project sponsor has expressed concern that the forecasted project implementation date coincides with the company's financial budget planning period.
Which two actions should the project manager take next to address this concern? (Choose two.)
Question