ExamGecko
Home Home / PMI / PMP

PMI PMP Practice Test - Questions Answers, Page 103

Question list
Search
Search

List of questions

Search

Related questions











A project manager is in charge of a software development project. A key stakeholder complains that they never received the functionality test status reports. The project manager provides the reports, and the stakeholder notices that an important functionality for their area was not tested.

Which tool should the project manager have used to prevent this situation?

A.
Issue log
A.
Issue log
Answers
B.
Project scope statement
B.
Project scope statement
Answers
C.
Stakeholder register
C.
Stakeholder register
Answers
D.
Project charter
D.
Project charter
Answers
Suggested answer: B

A team is not delivering the committed work. Cards are not moving on the kanban board, and the burndown chart shows that the sprint progress is slow.

What should the agile project manager do?

A.
Consider the use of alternative performance metrics.
A.
Consider the use of alternative performance metrics.
Answers
B.
Change the work in progress (WIP) limit to reflect the team's capacity.
B.
Change the work in progress (WIP) limit to reflect the team's capacity.
Answers
C.
Discuss the performance with senior leadership.
C.
Discuss the performance with senior leadership.
Answers
D.
Meet with the project team members who are slow in delivering tasks.
D.
Meet with the project team members who are slow in delivering tasks.
Answers
Suggested answer: D

A project manager is asked to negotiate between two team members who frequently have misunderstandings in order to reach an agreement that will advance the project. What should the project manager to?

A.
Establish common ground through collaboration and understanding the team members' needs
A.
Establish common ground through collaboration and understanding the team members' needs
Answers
B.
Organize a team-building event to improve the morale among team members
B.
Organize a team-building event to improve the morale among team members
Answers
C.
Encourage a positive ongoing relationship between both of the team members
C.
Encourage a positive ongoing relationship between both of the team members
Answers
D.
Coach and mentor the team members to build consensus and to resolve the ongoing conflict
D.
Coach and mentor the team members to build consensus and to resolve the ongoing conflict
Answers
Suggested answer: D

A project manager is working on a project for a startup company. The company launched cloudbased agile project management and DevOps training modules via the learning platform to support multiple self-paced and virtual learning formats. In a recent sprint, the quality assurance team failed to thoroughly inspect the modules before deployment, resulting in a poor customer experience.

Which of the following issues is the project manager facing?

A.
Nonconformance issue
A.
Nonconformance issue
Answers
B.
Escaped defect
B.
Escaped defect
Answers
C.
Unmet planned-to-done ratio
C.
Unmet planned-to-done ratio
Answers
D.
Undetected error
D.
Undetected error
Answers
Suggested answer: B

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?

A.
Meet with each team member separately and apply an appropriate approach with each one
A.
Meet with each team member separately and apply an appropriate approach with each one
Answers
B.
Assign multiple managers to the various teams and delegate all of the tasks to them
B.
Assign multiple managers to the various teams and delegate all of the tasks to them
Answers
C.
Explain to the team that the project manager is ultimately responsible for the delivery
C.
Explain to the team that the project manager is ultimately responsible for the delivery
Answers
D.
Approach the project sponsor and request help in discussing the project deliverables with team members
D.
Approach the project sponsor and request help in discussing the project deliverables with team members
Answers
Suggested answer: A

A product is undergoing its last iterative increment, and the project team is ready to make the final deployment. The company's financial manager is asking the project team to complete the deployment and close the project as soon as possible so it can be capitalized.

What should the project manager do?

A.
Expedite the final deployment and close the project.
A.
Expedite the final deployment and close the project.
Answers
B.
Ignore the stakeholder's request as there is a defined plan.
B.
Ignore the stakeholder's request as there is a defined plan.
Answers
C.
Update the acceptance criteria for the iteration.
C.
Update the acceptance criteria for the iteration.
Answers
D.
Check on the definition of done (DoD) for the project.
D.
Check on the definition of done (DoD) for the project.
Answers
Suggested answer: D

A project manager has been assigned to a corporate project management office (PMO). They are responsible for leading the development and rollout of updated project management procedures and templates that would include both predictive and agile approaches.

What should the project manager do after the documents are completed?

A.
Upload the files to the corporate website to be available for internal use
A.
Upload the files to the corporate website to be available for internal use
Answers
B.
Develop a training plan for all of the stakeholders to learn about the updates
B.
Develop a training plan for all of the stakeholders to learn about the updates
Answers
C.
Hire an external consultant to monitor the execution of the new procedures
C.
Hire an external consultant to monitor the execution of the new procedures
Answers
D.
Meet with the department managers to help them roll out the new procedures
D.
Meet with the department managers to help them roll out the new procedures
Answers
Suggested answer: B

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

A.
Update the stakeholder register.
A.
Update the stakeholder register.
Answers
B.
Consult the project sponsor.
B.
Consult the project sponsor.
Answers
C.
Refer to the resource management plan.
C.
Refer to the resource management plan.
Answers
D.
Modify the statement of work (SOW).
D.
Modify the statement of work (SOW).
Answers
Suggested answer: C

A project manager is working on a project that is required to deliver value on an incremental basis. Which action should the project manager take to enable successful project execution?

A.
Identify the tangible and intangible benefits.
A.
Identify the tangible and intangible benefits.
Answers
B.
Create a project schedule containing milestones.
B.
Create a project schedule containing milestones.
Answers
C.
Engage with the project sponsor to understand the scope.
C.
Engage with the project sponsor to understand the scope.
Answers
D.
Develop a comprehensive set of requirements.
D.
Develop a comprehensive set of requirements.
Answers
Suggested answer: B

A bank wants to initiate a new service for its customers that will also increase revenue. This service must comply with strict cyber regulation guidelines. Halfway through the project life cycle, the cyber regulations change, which has a large impact on the project.

What type of status report should the project leader present to the stakeholders?

A.
A report including the change control process tor the requested changes and the updated risk register
A.
A report including the change control process tor the requested changes and the updated risk register
Answers
B.
A report containing statistics, detailed tasks to be done, and an explanation of the impact of the changes
B.
A report containing statistics, detailed tasks to be done, and an explanation of the impact of the changes
Answers
C.
A report that includes a detailed risk mitigation plan and action items for complying with changes
C.
A report that includes a detailed risk mitigation plan and action items for complying with changes
Answers
D.
A report that is concise and simple, and that clearly states the impact the changes will have
D.
A report that is concise and simple, and that clearly states the impact the changes will have
Answers
Suggested answer: A
Total 1.477 questions
Go to page: of 148