Five project team members are working on a software development project. As the time line for the project is very tight, the members are working overtime to keep the project on schedule.
Recently, two members submitted resignations.
What should the project manager do?
A.
Acquire experienced additional resources from third-party suppliers.
B.
Assist the team to reallocate the task to the three team members.
C.
Acquire replacements by starting the hiring process immediately.
D.
Escalate to the project sponsor and seek approval for a schedule delay.