ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 976 - PMP discussion

Report
Export

Five project team members are working on a software development project. As the time line for the project is very tight, the members are working overtime to keep the project on schedule.

Recently, two members submitted resignations.

What should the project manager do?

A.
Acquire experienced additional resources from third-party suppliers.
Answers
A.
Acquire experienced additional resources from third-party suppliers.
B.
Assist the team to reallocate the task to the three team members.
Answers
B.
Assist the team to reallocate the task to the three team members.
C.
Acquire replacements by starting the hiring process immediately.
Answers
C.
Acquire replacements by starting the hiring process immediately.
D.
Escalate to the project sponsor and seek approval for a schedule delay.
Answers
D.
Escalate to the project sponsor and seek approval for a schedule delay.
Suggested answer: D
asked 23/09/2024
shikeba barakzei
34 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first