Question 977 - PMP discussion
During a project kickoff meeting, the client indicates that the benefits of the project will become the most important revenue stream for the company. The client needs to find opportunities to deliver value to their company as soon as possible.
What should the project manager do?
A.
Apply project schedule compression techniques to deliver benefits faster.
B.
Plan project iterations taking into consideration value delivery.
C.
Develop a project management plan to achieve the goals of the project faster.
D.
Align the goals of the project with the revenue goals of the company.