Question 978 - PMP discussion
A project manager forms a new virtual project team that will be leading the project subcontractors in various countries. The project manager notices that each of the team members comes from a different culture.
Which action should the project manager take to increase team cohesiveness?
A.
Execute a rotating relocation, where team members spend a certain amount of time in each of the countries.
B.
Empower the team and emphasize the project manager's trust in them.
C.
Arrange a weekly virtual meeting to allow team members to exchange their cultures.
D.
Require each team member to physically attend at least two meetings per year.