ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 979 - PMP discussion

Report
Export

A project in the execution phase is part of a large transformation program. The project manager for this project reports to a program manager and also heads the steering committee for this project. A steering committee meeting will be held in the following 2 weeks, during which the approach to measure the schedule performance of the project thus far will be presented.

What should the project manager do in preparation for this meeting?

A.
Prepare to demonstrate the cost-benefit ratio, business value, and return on investment (ROI) as the schedule performance metrics.
Answers
A.
Prepare to demonstrate the cost-benefit ratio, business value, and return on investment (ROI) as the schedule performance metrics.
B.
Update the cost performance index (CPI) and schedule performance index (SPI) to measure the performance of the project.
Answers
B.
Update the cost performance index (CPI) and schedule performance index (SPI) to measure the performance of the project.
C.
Prepare to explain that the schedule performance index (SPI), schedule variance (SV), and other performance metrics are being used.
Answers
C.
Prepare to explain that the schedule performance index (SPI), schedule variance (SV), and other performance metrics are being used.
D.
Inform the program manager that the project is using an agile approach and schedule performance metrics are not applicable.
Answers
D.
Inform the program manager that the project is using an agile approach and schedule performance metrics are not applicable.
Suggested answer: C
asked 23/09/2024
Dewald Van Schalkwyk
32 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first