A project manager is reviewing the documents for closing a phase when the customer calls to say that the project is not generating any value for the company. What should the project manager do?

A.
Wait to close the project until the customer is satisfied.
Answers
A.
Wait to close the project until the customer is satisfied.
B.
Validate the project scope, objectives, and outcomes with the customer.
Answers
B.
Validate the project scope, objectives, and outcomes with the customer.
C.
Analyze which activities will generate the most value for the project.
Answers
C.
Analyze which activities will generate the most value for the project.
D.
Perform a cost-benefit analysis for the project.
Answers
D.
Perform a cost-benefit analysis for the project.
Suggested answer: B