As part of project execution, a contractor proposed and conducted site acceptance tests and preimplementation technical training. However, during the implementation phase, the project manager notes a clear gap in the project team's competence in following the implementation of the technical requirements.

What should the project manager have done to avoid this situation?

A.
Ensured the training conducted by the contractor used standard methods
Answers
A.
Ensured the training conducted by the contractor used standard methods
B.
Reviewed the proposed training with the contractor
Answers
B.
Reviewed the proposed training with the contractor
C.
Performed a proper training needs assessment
Answers
C.
Performed a proper training needs assessment
D.
Prepared proper training outcome measurements
Answers
D.
Prepared proper training outcome measurements
Suggested answer: C