Question 984 - PMP discussion

Report
Export

The project manager received a claim from the client because the outcome delivered is not working properly. The project manager investigated the cause and realized that this deliverable was outsourced to an external provider, and was not made aware.

What primary tool would have helped the project manager identify this situation?

A.
Communications management plan
Answers
A.
Communications management plan
B.
Scope baseline
Answers
B.
Scope baseline
C.
Risk register
Answers
C.
Risk register
D.
Stakeholder register
Answers
D.
Stakeholder register
Suggested answer: D