A project manager is leading a team that is new to agile. During the kickoff meeting, one team member asks how risks will be managed using agile approaches.
How should the project manager respond?
A.
Risk management is a collaborative effort and will be managed during each iteration.
B.
Risks are managed by the project manager and forecasted at the beginning of each project.
C.
Risks will be managed during a retrospective session with all of the team members.
D.
Risks are managed by the team and they will be analyzed during risk management kickoff.
Your answer: