Question 991 - PMP discussion

Report
Export

For the second time in a week, one of the team members failed to deliver their assigned work. As a result, it is impossible for the team to achieve their agreed-upon target.

What should the project manager do?

A.
Insist that the team member maintain the agreed-upon rate of output to maintain the deadline.
Answers
A.
Insist that the team member maintain the agreed-upon rate of output to maintain the deadline.
B.
Review the project team's performance level and discuss areas for improvement.
Answers
B.
Review the project team's performance level and discuss areas for improvement.
C.
Discuss the issue with the team member to identify the root cause and work to resolve it.
Answers
C.
Discuss the issue with the team member to identify the root cause and work to resolve it.
D.
Seek a replacement who has the same skillset and availability as the team member.
Answers
D.
Seek a replacement who has the same skillset and availability as the team member.
Suggested answer: C