After releasing the first deliverable of the project, one of the impacted departments refused to use the system because they believe that it adds more work. What could the project manager have done to prevent this?
A.
Deployed a user survey
B.
Reviewed organizational standard policies
C.
Created an escalation plan
D.
Conducted a stakeholder analysis