A project team is executing a project to replace an existing system with a new one. A new project manager has been hired and observes that the team consist of professionals who have worked with the older system, and others who have little previous experience.
What should the project manager do to ensure project success?
A.
Evaluate the current effectiveness of the team and define development needs.
B.
Assign team member roles and responsibilities based on past experience.
C.
Allow each team member to use their individual strengths for project success.
D.
Request a performance assessment for the team from the functional manager.