During project execution, a client asks to add one more features to the product. After performing a change request analysis, the project manager realizes the necessary equipment will not be available in time to support this new feature, resulting in the project team being idle.

What should the project manager do next?

A.
Establish a contingency reserve.
Answers
A.
Establish a contingency reserve.
B.
Rent ready-made equipment.
Answers
B.
Rent ready-made equipment.
C.
Escalate the risk to senior management.
Answers
C.
Escalate the risk to senior management.
D.
Perform integrated change control.
Answers
D.
Perform integrated change control.
Suggested answer: D