Question 1012 - PMP discussion
A project needs to acquire a large volume of electrical supplies on a weekly delivery cycle. There are many suppliers interested in partnering, so the project manager feels confident they can negotiate a good price.
What should the project manager do first in order to ensure the best overall value in the future contract?
A.
Meet with the project sponsor to learn more about past contracting efforts for electrical supplies.
B.
Contact each of the potential suppliers to understand their price schedules for the required supplies.
C.
Identify the policies, procedures, guidelines, and legal parameters that are required in the contract.
D.
Create a time-based bill of materials containing the supplies that need to be delivered each week.
Your answer: