In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?

A.
Empower the team members to do their work.
Answers
A.
Empower the team members to do their work.
B.
Work with the team to develop a risk response plan.
Answers
B.
Work with the team to develop a risk response plan.
C.
Send an email to human resources (HR) about this situation.
Answers
C.
Send an email to human resources (HR) about this situation.
D.
Inform the project sponsor about this situation.
Answers
D.
Inform the project sponsor about this situation.
Suggested answer: B