A project manager is transitioning from a predictive life cycle project to a new agile project. How should the project manager manage and control the scope for the new project?
A.
Estimate the work the team can complete and define story sizes to keep the project under control
B.
Spend a short amount of time defining the scope and building prototypes to refine the requirements
C.
Develop a plan to complete more work in less time
D.
Create a scope baseline and put the rest as backlog activities