A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?

A.
Project schedule
Answers
A.
Project schedule
B.
Issue log
Answers
B.
Issue log
C.
Risk register
Answers
C.
Risk register
D.
Change request
Answers
D.
Change request
Suggested answer: B