ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1021 - PMP discussion

Report
Export

A project manager is in charge of a software development project. A key stakeholder complains that they never received the functionality test status reports. The project manager provides the reports, and the stakeholder notices that an important functionality for their area was not tested.

Which tool should the project manager have used to prevent this situation?

A.
Issue log
Answers
A.
Issue log
B.
Project scope statement
Answers
B.
Project scope statement
C.
Stakeholder register
Answers
C.
Stakeholder register
D.
Project charter
Answers
D.
Project charter
Suggested answer: B
asked 23/09/2024
Tanvir Anjum
42 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first