List of questions
Related questions
Question 1026 - PMP discussion
A product is undergoing its last iterative increment, and the project team is ready to make the final deployment. The company's financial manager is asking the project team to complete the deployment and close the project as soon as possible so it can be capitalized.
What should the project manager do?
A.
Expedite the final deployment and close the project.
B.
Ignore the stakeholder's request as there is a defined plan.
C.
Update the acceptance criteria for the iteration.
D.
Check on the definition of done (DoD) for the project.
Your answer:
0 comments
Sorted by
Leave a comment first