Question 1027 - PMP discussion
A project manager has been assigned to a corporate project management office (PMO). They are responsible for leading the development and rollout of updated project management procedures and templates that would include both predictive and agile approaches.
What should the project manager do after the documents are completed?
A.
Upload the files to the corporate website to be available for internal use
B.
Develop a training plan for all of the stakeholders to learn about the updates
C.
Hire an external consultant to monitor the execution of the new procedures
D.
Meet with the department managers to help them roll out the new procedures