Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

A.
Update the stakeholder register.
Answers
A.
Update the stakeholder register.
B.
Consult the project sponsor.
Answers
B.
Consult the project sponsor.
C.
Refer to the resource management plan.
Answers
C.
Refer to the resource management plan.
D.
Modify the statement of work (SOW).
Answers
D.
Modify the statement of work (SOW).
Suggested answer: C