Question 1037 - PMP discussion
A construction company recently won the bid for a project to build a cable bridge. A project charter has been prepared and a project manager has been assigned. The project manager is creating a work breakdown structure (WBS) for the project.
To what level should the project manager decompose their project?
A.
To the lowest level where cost and duration can be estimated and managed
B.
To the level where the highest level of quality is maintained
C.
To level four of the schedule for bridge construction
D.
To the level where the bridge can be constructed safely