List of questions
Related questions
Question 1038 - PMP discussion
A project manager is working on a global project. One team member is from a different country and is unable to attend project meetings on a regular basis. Because of this, other team members have started questioning the need for the project meeting. This issue is affecting the time line deliverable and quality parameters.
What should the project manager do to manage the project deliverables?
A.
Define the rules for the project meeting.
B.
Make it mandatory for all members to attend all project meetings.
C.
Make it mandatory for all members to discuss their work at project meetings.
D.
Define the agenda for the project meeting.
Your answer:
0 comments
Sorted by
Leave a comment first