A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?
A.
Initiate a risk response strategy from the risk register.
B.
Perform a detailed assessment to analyze the impact.
C.
Reject the changes as the project is in the final stages.
D.
Use schedule compression methods to alter the critical path.