A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?

A.
Initiate a risk response strategy from the risk register.
Answers
A.
Initiate a risk response strategy from the risk register.
B.
Perform a detailed assessment to analyze the impact.
Answers
B.
Perform a detailed assessment to analyze the impact.
C.
Reject the changes as the project is in the final stages.
Answers
C.
Reject the changes as the project is in the final stages.
D.
Use schedule compression methods to alter the critical path.
Answers
D.
Use schedule compression methods to alter the critical path.
Suggested answer: B