Question 1048 - PMP discussion
A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously. this defect negatively affected the project schedule.
What should the project manager do first?
A.
Check the organizational process assets (OPAs).
B.
Update the risk management plan.
C.
Acquire knowledgeable resources.
D.
Extend the timeline of the project.