Question 1049 - PMP discussion
A project manager has taken over an agile project. There have been several issues during product development due to unclear product requirements.
How should the project manager resolve this issue?
A.
Assist the team in estimating project tasks such as milestones and story points.
B.
Gather the project team and product owner to find a solution design.
C.
Review issues and identify opportunities for improvement that add value to the product.
D.
Ask the team to rework the definition of done (DoD) before items can be pulled into the backlog.
Your answer: