In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.

What should the project manager do to handle this situation?

A.
Coach the team members on agile processes and knowledge.
Answers
A.
Coach the team members on agile processes and knowledge.
B.
Perform team-building activities and enhance collaboration.
Answers
B.
Perform team-building activities and enhance collaboration.
C.
Identify the team members who are impacting low morale.
Answers
C.
Identify the team members who are impacting low morale.
D.
Give team members more authority to make decisions.
Answers
D.
Give team members more authority to make decisions.
Suggested answer: B