Question 1055 - PMP discussion

Report
Export

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component managed by an external vendor. How should the project manager address the team member's concern?

A.
Implement fast tracking to reduce the impact of the delay on the sprint.
Answers
A.
Implement fast tracking to reduce the impact of the delay on the sprint.
B.
Ask the team member to provide details to address the issue with the vendor.
Answers
B.
Ask the team member to provide details to address the issue with the vendor.
C.
Ask the team member to resolve the issue independently to minimize further delays.
Answers
C.
Ask the team member to resolve the issue independently to minimize further delays.
D.
Update the communications management plan to prevent future reoccurrence.
Answers
D.
Update the communications management plan to prevent future reoccurrence.
Suggested answer: B