ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1056 - PMP discussion

Report
Export

During the last iteration of a hybrid project., one of the key members of the team wants to leave the project. What should the project manager do to address this concern?

A.
Update the burndown chart to reflect this resource's absence.
Answers
A.
Update the burndown chart to reflect this resource's absence.
B.
Keep activities as planned regardless of the resource change.
Answers
B.
Keep activities as planned regardless of the resource change.
C.
Have a meeting with the resource to understand the issue.
Answers
C.
Have a meeting with the resource to understand the issue.
D.
Request an additional resource to finish the project.
Answers
D.
Request an additional resource to finish the project.
Suggested answer: C
asked 23/09/2024
JULIAN SSEMALULU
21 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first