A project manager finds a mistake with an important server acquisition. The acquisition was expected for a critical path activity but has not arrived yet, causing significant impacts on time and cost. The team member responsible for this activity argues that they sent several emails to the supplier but received no reply.

Which document should be used to help avoid this kind of situation?

A.
Communications management plan
Answers
A.
Communications management plan
B.
Escalation process
Answers
B.
Escalation process
C.
Statement of work (SOW)
Answers
C.
Statement of work (SOW)
D.
Stakeholder register
Answers
D.
Stakeholder register
Suggested answer: B