Question 1059 - PMP discussion

Report
Export

After 35 years of service, a company's CEO has retired. The new CEO is planning to digitally transform the company and has assigned a new project manager to assist in this endeavor. The initial backlog has been created and agreed upon, and the team members have been assigned.

What should the project manager do before the project kick-off meeting?

A.
Perform integration management activities to consolidate the plans.
Answers
A.
Perform integration management activities to consolidate the plans.
B.
Compare the team's expertise against the project requirements.
Answers
B.
Compare the team's expertise against the project requirements.
C.
Conduct a backlog refinement and identify the key activity to start with.
Answers
C.
Conduct a backlog refinement and identify the key activity to start with.
D.
Review the project's environment to understand the organizational culture.
Answers
D.
Review the project's environment to understand the organizational culture.
Suggested answer: D