A company is starting a new agile project with a team that has expertise working on these kinds of projects. During the backlog refinement meeting, the team realizes that they are not completing the estimations because some key information is missing.

What should the project manager do?

A.
Ask to postpone the iteration planning because the estimation is not complete.
Answers
A.
Ask to postpone the iteration planning because the estimation is not complete.
B.
Ask the product owner to review the stories with stakeholders prior to planning.
Answers
B.
Ask the product owner to review the stories with stakeholders prior to planning.
C.
Review the project backlog with the product owner before estimating the stories.
Answers
C.
Review the project backlog with the product owner before estimating the stories.
D.
Review the previous project estimations and assign them to the stories.
Answers
D.
Review the previous project estimations and assign them to the stories.
Suggested answer: C