Question 1062 - PMP discussion
A project is starting its third iteration out of six. During planning, the team realized that all of the requirements were not defined clearly enough to start working.
What should the project manager do?
A.
Review and replace the unclear requirements with ones that are clear.
B.
Update the issue log and escalate it to the project sponsor.
C.
Meet with the product owner to review the project backlog.
D.
Invite key users to the next daily meeting to get requirement clarification.