A project team is working to deliver a solution to manage nationwide crisis relief operations. The project team is spending most of its time in meetings with end users. The meetings have been slowing down project progress.

What should the project manager do to keep the deployment on track while obtaining stakeholder approval?

A.
Inform the stakeholders that a daily meeting will take place at a specific time and ask them to share their feedback during this time.
Answers
A.
Inform the stakeholders that a daily meeting will take place at a specific time and ask them to share their feedback during this time.
B.
Stop attending meetings, start development with what was collected so far. and define a date for the first delivery of the solution.
Answers
B.
Stop attending meetings, start development with what was collected so far. and define a date for the first delivery of the solution.
C.
Ask the project sponsor to attend the meetings on behalf of the team while the team is working on the development.
Answers
C.
Ask the project sponsor to attend the meetings on behalf of the team while the team is working on the development.
D.
Put all of the requirements, priorities, and progress on a visible board, share it with all entities, and decrease the number of meetings.
Answers
D.
Put all of the requirements, priorities, and progress on a visible board, share it with all entities, and decrease the number of meetings.
Suggested answer: D