Question 1067 - PMP discussion
In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?
A.
Anticipate, alert, and follow the risk management process.
B.
Discuss, educate, and follow the communications management process
C.
Detect, track, and follow the issue management process
D.
Promote, inspire, and follow the stakeholder engagement process