Question 1068 - PMP discussion
An agile project is running its second iteration out of six. A marketing director, who is a key stakeholder, contacts the project lead for a high-level report of the project.
What should the project lead do?
A.
Ask the product owner to develop the new report based on the iteration information.
B.
Develop the requested report based on the iteration information.
C.
Explain to the stakeholder that the key indicators are by iteration.
D.
Tell the stakeholder that a new report will be produced at the end of the iteration.
Your answer: