Question 1070 - PMP discussion
A project manager has commissioned a design study from a consulting firm to investigate a number of alternatives. The project manager has a strict policy on the cost of the study and has established a number of cost triggers and trend analyses.
Which tool is the project manager using?
A.
Time and materials (T&M) contract
B.
S-curve analysis
C.
Earned value (EV)
D.
Control chart