Question 1071 - PMP discussion
A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the system in stages. However, the operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?
A.
Include knowledge transfer sessions between the project and operations teams at every stage.
B.
Prepare detailed documentation to be shared with the operations team during project closure.
C.
Change the project management plan to add a final stage for product handoff to the operations team.
D.
Create a lessons learned register to include operations team training for future projects.