ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1077 - PMP discussion

Report
Export

A project manager noticed that a team member has been struggling with some tasks, which may ultimately impact the completion date. Team morale is low because they will not get the expected bonus if they do not finish on time.

What should the project manager do next?

A.
Update the project schedule and budget estimates.
Answers
A.
Update the project schedule and budget estimates.
B.
Ask the client to approve a delay in the project schedule.
Answers
B.
Ask the client to approve a delay in the project schedule.
C.
Acknowledge the team for their accomplishments, encourage them, and offer assistance to avoid future delays.
Answers
C.
Acknowledge the team for their accomplishments, encourage them, and offer assistance to avoid future delays.
D.
Ask the human resources (HR) department to replace the team member and add an additional resource.
Answers
D.
Ask the human resources (HR) department to replace the team member and add an additional resource.
Suggested answer: C
asked 23/09/2024
sushil divate
35 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first