Question 1077 - PMP discussion
A project manager noticed that a team member has been struggling with some tasks, which may ultimately impact the completion date. Team morale is low because they will not get the expected bonus if they do not finish on time.
What should the project manager do next?
A.
Update the project schedule and budget estimates.
B.
Ask the client to approve a delay in the project schedule.
C.
Acknowledge the team for their accomplishments, encourage them, and offer assistance to avoid future delays.
D.
Ask the human resources (HR) department to replace the team member and add an additional resource.