Question 1078 - PMP discussion
One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests that this might just be a small task.
What should the project manager do?
A.
Perform a qualitative risk analysis.
B.
Coordinate design document preparation.
C.
Request further clarification of the requirement.
D.
Manage the engagement of this stakeholder.