One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests that this might just be a small task.

What should the project manager do?

A.
Perform a qualitative risk analysis.
Answers
A.
Perform a qualitative risk analysis.
B.
Coordinate design document preparation.
Answers
B.
Coordinate design document preparation.
C.
Request further clarification of the requirement.
Answers
C.
Request further clarification of the requirement.
D.
Manage the engagement of this stakeholder.
Answers
D.
Manage the engagement of this stakeholder.
Suggested answer: C