Company A has a culture of adhering to policies and procedures. A project manager is applying an agile approach to their in-house software development project, but even with training, they are still unable to deliver efficiently.

What should the project manager do first to improve this situation?

A.
Empower and coach the team members to focus on project delivery results.
Answers
A.
Empower and coach the team members to focus on project delivery results.
B.
Identify key team members who can influence others to contribute efficiently.
Answers
B.
Identify key team members who can influence others to contribute efficiently.
C.
Follow company procedures and retrain team members on the agile approach.
Answers
C.
Follow company procedures and retrain team members on the agile approach.
D.
Ask company management to delay the project and grant it additional time.
Answers
D.
Ask company management to delay the project and grant it additional time.
Suggested answer: A