A project manager is using a hybrid approach for a project. The project team created and reviewed the risk log with the stakeholders at the beginning of the project. However, midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies.

When should the risks be reviewed to ensure alignment between the project team and the stakeholders?

A.
During each steering committee meeting
Answers
A.
During each steering committee meeting
B.
During the retrospectives
Answers
B.
During the retrospectives
C.
During the risk register update
Answers
C.
During the risk register update
D.
During each iteration and review
Answers
D.
During each iteration and review
Suggested answer: D