Question 1082 - PMP discussion

Report
Export

A project is in the planning phase. The project manager notices that the available engineers do not have the required skills. Since outsourcing is not an option for this project, the project manager asks human resources (HR) to hire or assign engineers with the required skills.

However, the company cannot afford this at the moment.

What should the project manager do first?

A.
Introduce a mentoring program to facilitate knowledge sharing.
Answers
A.
Introduce a mentoring program to facilitate knowledge sharing.
B.
Change the scope to include only the work that the team is qualified to do.
Answers
B.
Change the scope to include only the work that the team is qualified to do.
C.
Add extra time for training during the course of the project.
Answers
C.
Add extra time for training during the course of the project.
D.
Use the management reserve to obtain the needed resources.
Answers
D.
Use the management reserve to obtain the needed resources.
Suggested answer: C