List of questions
Related questions
Question 1182 - PMP discussion
During the execution phase of a project, one of the customer's stakeholders keeps requesting changes to the scope every week. Which three actions should the project manager take to resolve this issue? (Choose three.)
A.
Update the relevant project documents with this obstacle.
B.
Highlight the impacts of the changes during the next project meeting.
C.
Adjust the project management plan to include the changes in scope.
D.
Continue the execution as planned and defer the changes to a future phase.
E.
Schedule a meeting with the customer to align the approach.1
Your answer:
0 comments
Sorted by
Leave a comment first