Question 1185 - PMP discussion
A project that has to be delivered by the targeted date has been delayed due to an unforeseen risk occurrence. How should the project manager compress the project to ensure the completion date is not affected?
A.
Add more project resources
B.
Fast-track the project
C.
Reduce the project scope
D.
Increase the project cost
Your answer: