Question 1186 - PMP discussion
A client's company announces a reorganization, which includes changes in the senior management involved in the project. The new project sponsor is asking to put the project on hold until they review the scope.
What should the project manager do next?
A.
Wait for a new project scope from the new project sponsor
B.
Discuss the requirements and update the project management plan with the new sponsor
C.
Discuss the issue with the project team and update the project management plan
D.
Amend the risk register and provide suggested mitigation strategies